On completion of the plant, all units were tested from a mechanical point of view and all apparent defects were made good. The plant was then painted ad was not operated again until after the official opening.
Reference:
Van der Walt, P. 1958. Proposed programme of work for the coal preparation pilot plant February - July 1958. http://hdl.handle.net/10204/12835 .
Van der Walt, P. (1958). Proposed programme of work for the coal preparation pilot plant February - July 1958 Retrieved from http://hdl.handle.net/10204/12835
Van der Walt, PJ Proposed programme of work for the coal preparation pilot plant February - July 1958. 1958. http://hdl.handle.net/10204/12835
Van der Walt P. Proposed programme of work for the coal preparation pilot plant February - July 1958. 1958 [cited yyyy month dd]. Available from: http://hdl.handle.net/10204/12835